On the 7th July 2003 Railtrack are to commence
work on the River Llynfi just 100yrds above the junction
with the Ogmore. Repairs and improvements to an existing
railway bridge situated adjacent to Pandy Park, Tondu,
has b ecome
necessary for public safety. The works are planned for
10 weeks, however after consultation between the Ogmore
Anglers Association and Railtrack, a maximum of 4 weeks
wet work is planned. Thus, preventing a minimum of discoloration
to the river course and silt movement. The main river
works are planned to take place during the earlier parts
of the week, Mondays, Tuesdays, Wednesdays, to avoid any
inconvenience to the ogmore members, but unfortunately
there are going to be times during the days to come when
the river will be discolored and will undoubtedly effect
the daytime fishing.
|